13.8 kV 10.5 MVA Substation Transformer Project for a Customer in Vietnam

Jun 21, 2024

Leave a message

Customer Requirement: 13.8 kV, 10.5 MVA Substation Transformer

On 20 June, a customer in Vietnam contacted the transformer manufacturer through the website with a request for a 10.5 MVA three-phase substation transformer rated 13.8 kV on the high voltage side and 2.4 kV on the low voltage side. The unit was needed for a replacement project, and the customer was evaluating a new supplier for the first time, so both the technical response and the transparency of the manufacturing process carried weight in the decision.

Replacement work has a particular constraint that new-build projects do not: the transformer has to fit the existing foundation, cable terminations and protection scheme. The specification therefore had to be confirmed against the installed equipment before design started, not after.

Technical Solution Preparation

Once the technical parameters had been received, the engineering team prepared a complete solution within one week, drawing on more than a decade of project experience in the Vietnamese market. Working to that regional experience matters, because ambient temperature, humidity, lightning activity and the local grid connection practice all influence the insulation level, the cooling arrangement and the protection settings that the transformer must support.

The solution defined the rated voltage ratio, the connection group, the impedance window needed for correct parallel operation with the existing network, and the cooling class required to hold 10.5 MVA at the site ambient temperature. Insulation levels and dielectric test requirements were aligned with IEC 60076-3, while the general transformer requirements and routine test schedule followed IEC 60076-1.

Quotation, Factory Visit and Design Approval

A detailed quotation was issued covering the transformer price, the technical data sheet, outline drawings and the test reports that would be supplied at the end of manufacture. The customer asked for a virtual factory tour and a meeting at the production facility to inspect the equipment and discuss the details in person, in order to gain confidence in the supplier's capability before committing to the order.

Outline drawing prepared to the customer's requirements within one week and confirmed with the customer.

Production drawings issued and approved within two to three weeks after outline confirmation.

Regular progress reports, including visual updates from the workshop, shared throughout manufacture.

Witness points and inspection stages agreed in advance so that the customer knew when to expect each update.

Confirming the drawings before material release is the step that protects the delivery date. Corrections made on a drawing cost nothing, while corrections made after coil winding and tank fabrication cost both time and money.

Quality Assurance and Testing

Rigorous quality testing was carried out before shipment, including no-load loss and load loss measurement, which confirm both the efficiency of the magnetic circuit and the impedance of the winding assembly. The results were compared against the guaranteed values stated in the technical agreement.

Winding resistance and voltage ratio verification on all tapping positions.

No-load loss and excitation current measurement at rated voltage.

Load loss and short circuit impedance measurement at rated current.

Applied voltage and induced overvoltage dielectric routine tests.

Oil quality and dielectric tests on the insulating liquid.

Functional checks of cooling control, temperature indication and protection devices.

A third-party inspection company verified the quality control process through video conferencing, which allowed the customer to witness the critical stages without travelling to the factory. Remote witnessing keeps the verification independent while avoiding the cost and delay of an international inspection visit.

Packaging, Shipping and After-Sales Support

The transformers were packed to strict packaging standards for sea transport, with the active part secured against movement, bushings and accessories packed separately, and moisture protection applied for the voyage. Shipment was arranged promptly to Shanghai Port, from where the cargo was forwarded to the customer's site in Vietnam.

After delivery, online training courses were provided on transformer installation and operation, covering foundation and alignment requirements, oil filling and soak procedure, cooling and protection commissioning, and the checks required before energisation. This support stage matters as much as the manufacturing stage: a correctly built transformer that is incorrectly installed or energised will not reach its intended service life, and post-delivery training shortens the learning curve for the operating team and reduces the risk of avoidable downtime on a unit that has replaced an existing machine.

FAQ

Q: What were the key ratings of this transformer?
The unit was a three-phase substation transformer rated 10.5 MVA with a 13.8 kV high voltage winding and a 2.4 kV low voltage winding, supplied for a replacement project in Vietnam.

Q: How quickly was the technical solution prepared?
The complete technical solution was developed within one week of receiving the customer's parameters, followed by an outline drawing within one week and approved production drawings within two to three weeks.

Q: Which tests were performed before shipment?
No-load loss and load loss testing was carried out together with ratio, winding resistance, impedance and dielectric routine tests, and a third-party inspection company verified the quality control process by video conference.

Q: Why is no-load loss testing important for a replacement unit?
Because the transformer will run continuously for many years, the no-load loss directly determines the energy cost of ownership, and measuring it confirms the quality of the core assembly against the guaranteed value.

Q: How was the transformer transported?
The unit was packed to strict packaging standards for sea freight and shipped promptly to Shanghai Port, with accessories packed separately and moisture protection applied for the voyage.

Q: What support is provided after delivery?
Online training courses covering installation and operation are provided after delivery, addressing foundation alignment, oil filling and soak, cooling and protection commissioning, and the pre-energisation checks.